Liverpool takes 'hyper-sensitive' approach to flyover destruction

 

Work to demolish the Churchill Way flyovers in Liverpool will get underway this week using what the council called an ‘innovative methodology’ to keep traffic flowing.

Liverpool City Council said the deconstruction will happen without the need for a three-month road closure on two major arterial roads - servicing Liverpool city centre and Queensway Tunnel. 

The works will begin on Monday (2 September) and are due to be to be completed in December.

The ‘hyper-sensitive’ process, devised collaboratively between Amey Consulting, GRAHAM and their specialist contractors, will cost £6.75m and see the half-century old structures come down in sections up to 25 metres in length.

”Local

The flyovers consist of two separate roads linking Lime Street to Dale Street (south flyover) and Tithebarn Street (north flyover), running directly behind the city’s museums and galleries in William Brown Street.

They were closed in September 2018 following the discovery of construction flaws.

Liverpool mayor Joe Anderson said: ‘The Churchill Way flyovers are a relic of a cancelled highways plan from half a century ago and given the overwhelming weight of evidence from independent experts about their safety, their removal was the only viable option. We simply have no choice but to take them down as soon as possible.

‘This deconstruction is going to be a complex process. It cannot be done overnight and a lot of thought has gone into the methodology to ensure the inconvenience to city centre traffic and surrounding buildings is kept to a minimum – but people need to understand that this is going to cause a huge amount of unavoidable disruption.’

The council said motorists will at times be advised to only drive if absolutely necessary, and instead to walk, cycle or take the bus or train.

It added that the process has also been devised to minimise vibrations to protect antique art and cultural collections, as well as wildlife housed at the Walker Art Gallery, Central Library and World Museum Liverpool – all of which sit next to the south flyover.

Each span – weighing between 300 and 600 tonnes – will be temporarily supported, before being cut free and moved on to a special transporter to a nearby compound, where it will be lowered to ground level, cut into smaller sections and removed off site to be crushed.

A total of 20 spans and supporting piers will be removed over a four-month period.

Register now for full access


Register just once to get unrestricted, real-time coverage of the issues and challenges facing UK transport and highways engineers.

Full website content includes the latest news, exclusive commentary from leading industry figures and detailed topical analysis of the highways, transportation, environment and place-shaping sectors. Use the link below to register your details for full, free access.

Already a registered? Login

 
comments powered by Disqus